Painting to be Completed This Week plus a Few Odd Ends

Painting to be Completed This Week plus a Few Odd Ends

The last few weeks have been remaining outstanding jobs required to be finalised by the trades; final coats of paint, plumber fit off, electrical fit off, shower screen and mirror install. From our last inspection, we raised the following concerns which are currently being reviewed: One of our…

Finalising of Internal Carpentry and Commencement of Tiling – Lock-Up Stage

Finalising of Internal Carpentry and Commencement of Tiling – Lock-Up Stage

Dane has been great during this transition period as our new site supervisor.  He’s been responsive to emails and quite easy going in terms of approach.  His fortnightly email this week included the completion of internal wood works and tiling to commence in the wet areas. Our front door…